R&D

Achievements

R&D Achievements

Explore the diverse research and development achievements of our Technology Research Lab.

Nuclear-related R&D

Project NamePeriodRemarks
Localization of Steam Generator Moisture Separator2018.10~2021.09Large Nuclear Plant
CLP Liner Plate Repair Cutting Equipment2020.10~2021.10Large Nuclear Plant
Multipurpose Small Modular Reactor Mockup2020.10~2023.12SMR
Pressurizer Test Article Development2021.07~2022.11SMR
CVAP (Comprehensive Vibration Analysis) Scale Model Development2021.07~2022.12SMR
Auto-Cladding Welding Device Development2022.07~2024.07SMR
CASK Welding Material & Technology Development2023.01~2024.12Large Nuclear Plant
CRDM (Control Rod Drive Mechanism)2023.12~2024.12SMR
Fuel Assembly Assembly Device2024.05~2024.12SMR
Mock Fuel Assembly for Commissioning2024.05~2025.12SMR

Fusion-related R&D

Project NamePeriod
Thermal Shield of ITER Project2013.10~2020.12
DSM Diagnostic Port #18 Mockup2021.12~2022.12
LP02 Diagnostic Device2024.07~2025.10
Vacuum Vessel Irregular Port #32024.08~2025.10

Other R&D

Project NamePeriod
Development of Drive System for Solar Tracker2010.06~2011.06
Development of High-speed Planetary Gear Universal Attachment2011.12~2013.11
Attitude Rotation System for Marine Engine Machining2013.06~2014.06

Reference Images

  • Moisture Separator for Large Nuclear Power Plant

  • Auto-Cladding Welding Device

  • Cutting Equipment for Containment Liner Plate (CLP) Maintenance